NAME OF PROJECT | CONTRACTOR | COST | LOCATION | CONSTRUCTION & TARGET DATES | FUND SOURCE | COMPLETION DATE | STATUS |
2016 | |||||||
6-Storey Science and Technology Center with Roof deck | DUROS Development Corporation | 95,441,852.98 | CTU Main | 2/12/2016 5/15/2017 | GAA=50M & STF=40M + 8.37M | 6/29/2017 | Completed |
Rehabilitation of College of Technology Building | MCEE Construction Corporation | 16,908,894.56 | CTU Main | 3/14/2016 1/14/2017 | GAA=18.61M | 1/7/2017 | Completed |
Rehabilitation of ICT Building & Construction of Classrooms at Roofdeck | DSJP Construction | 4,597,354.34 | CTU Main | 7/10/2016 12/6/2016 | STF=5M | 6/12/2016 | Completed |
Canteen & Phase 2 Library | BL Pangan Construction | 21,000,000.00 | CTU Main | 10/21/2017 8/16/2018 | GAA=7.647M & STF=16M | 8/16/2018 | Completed |
Rehabilitation of Centennial Building and Construction of Roofdeck Function Hall | BD Revalde Construction Corp. | 23,912,246.40 | CTU Main | 10/30/2016 6/27/2017 | STF=24M | 6/27/2017 | Completed |
Rehabilitation of Engineering Building | MCEE Construction Corporation | 7,147,613.88 | CTU Main | 8/30/2016 2/25/2017 | STF=8.439M | 2/25/2017 | Completed |
Repainting of Education and Administration Building | MARLJAVIS Construction, Inc. | 3,851,696.61 | CTU Main | 11/24/2016 6/5/2017 | STF=4.3M | 5/27/2017 | Completed |
Center for Studies in Biodiversity Building | San Narciso Builders Corporation | 13,381,696.61 | CTU Argao | 10/13/2016 5/31/2017 | GAA=15M | 7/8/2017 | Completed |
1-Storey, 3-Classroom Building with Roof deck | CELJEM Construction and Development Corporation | 5,227,698.52 | CTU Argao | 12/13/2016 6/10/2017 | GAA=5.4M | 6/10/2017 | Completed |
Center for Studies in Biotechnology Building | DSJP Construction | 14,499,117.88 | CTU Barili | 12/1/2016 7/28/2017 | GAA=15M | 7/28/2017 | Completed |
Rehabilitation of School Building | DUROS Development Corporation | 16,488,993.71 | CTU Daanbantayan | 10/4/2016 6/30/2017 | GAA=17M | 6/30/2017 | Completed |
Classrooms | Hoppers’ Builders | 7,542,134.59 | CTU Moalboal | 6/10/2016 12/6/2016 | GAA=6M & STF=1.8M | 1//29/2017 | Completed |
Supply of Labor, Materials and Equipment for the Construction of Exterior Walls, Campus Director’s Office and Phase 1 Library | Cbush Construction | 4,492,803.27 | CTU Naga Extension | 12/5/2016 6/2/2017 | STF=4.97M | 6/2/2017 | Completed |
2-Storey Classroom Building & Perimeter Fence | BT Construction and General Services | 11,320,415.61 | CTU Pinamungahan | 12/15/2016 7/12/2017 | GAA=12M | 7/12/2017 | Completed |
Design and Build of Covered Court | San Narciso Builders Corporation | 12,631,376.00 | CTU Carmen | 4/14/2016 6/6/2017 | STF=13M | 1//29/2017 | Completed |
Supply of Labor, Materials and Equipment for the Rehabilitation of Exterior Walls, Ceiling, Roofing, Flooring and Comfort Rooms of Activity Center | GRAM Construction and Supply | 4,973,622.26 | CTU Danao | 12/30/2016 6/27/2017 | STF=5M | 6/27/2017 | Completed |
2017 | |||||||
Engineering Building | BT Construction and General Services | 12,932,701.83 | CTU Dumanjug | 10/2/2017 6/28/2018 | GAA=10M & STF=5M | 6/28/2018 | Completed |
Perimeter Fence (South Side) | BT Construction and General Services | 1,751,287.96 | CTU Dumanjug | 1/7/2018 5/6/2018 | STF=1.8M | 5/6/2018 | Completed |
Extension of Technology Building I (Phase 3) | BL Pangan Construction | 39,278,034.67 | CTU Main | 12/30/2017 3/12/2018 | GAA=20M & STF=20M | Ongoing | |
Conversion of Makeshift Classrooms to Administration Offices & Restroom | Gram Construction and Supply | 4,251,689.00 | CTU Main | 12/15/2017 4/13/2018 | STF=5M | 4/13/2018 | Completed |
Research and Technology Building (Phase 1) | DSJP Construction | 13,388,984.00 | CTU Moalboal | 11/24/2017 8/20/2018 | GAA=14.55M | 1/10/2018 | Completed |
Research Development and Engineering Building | MCEE Construction Corporation | 14,004,658.33 | CTU Danao | 10/11/2017 8/7/2018 | GAA=20M | 9/25/2018 | Completed |
Education Builing at CTU | MARLJAVIS Construction, Inc. | 14,921,111.00 | CTU Danao | 12/18/2017 9/13/2018 | STF=15M | 9/13/2018 | Completed |
3-Storey Engineering Building (Phase 1) | JARC Construction and Marine Services Corporation | 8,419,504.89 | CTU Tuburan | 10/13/2017 7/9/2018 | GAA=10M | 7/9/2018 | Completed |
Research Development and Engineering Building | CELJEM Construction and Development Corporation | 14,518,338.02 | CTU Carmen | 12/5/2017 8/31/2018 | STF=15M | 8/31/2018 | Completed |
Expansion of Library | Ascentia Construction, Inc. | 9,068,844.89 | CTU Daanbantayan | 10/8/2017 6/4/2018 | GAA=10M | 6/4/2018 | Completed |
Proposed Construction of 2nd floor of the 2-Storey Academic Building | Ascentia Construction, Inc. | 7,979,886.22 | CTU Daanbantayan | 2/22/2018 10/19/2018 | STF=8M | 12/28/2018 | Completed |
Construction and/or Rehabilitation of Multi-Purpose Building | JARC Construction and Marine Services Corporation | 3,345,000.00 | CTU Tuburan | 1/1/2018 4/30/2018 | STF=3.45M | 4/30/2018 | Completed |
Repair and Improvement of Structure/Facilities | BT Construction and General Services | 4,877,379.92 | CTU Argao | 4/11/2018 10/7/2018 | GAA=3.5M & STF=1.5M | 1/12/2018 | Completed |
Supply of Labor, Materials and Equipment for the Construction of Classrooms at 3rd Floor, Rehabilitation of Exterior Walls, and Phase 2 Library | DUROS Development Corporation | 11,997,815.49 | CTU Naga | 12/13/2017 8/9/2018 | STF=12M | 8/3/2018 | Completed |
2018 | |||||||
6-Storey Multi-Purpose Building & Perimeter Fence | Ascentia Construction, Inc. | 33,899,987.08 | CTU Main | 11/10/2018 7/7/2019 | GAA=35M | Ongoing | |
Center for Limnological Aquatic Biodiversity & Mariculture Studies Building | Barr Steel Construction | 9,645,235.78 | CTU San Francisco | 11/22/2018 6/19/2019 | GAA=10M | Ongoing | |
Campus Development Projects | Barr Steel Construction | 14,490,772.49 | CTU San Francisco | 6/21/2018 3/17/2019 | GAA=15M | Ongoing | |
Library Building | DSJP Construction | 14,521,832.08 | CTU Argao | 11/22/2018 8/18/2019 | GAA=15M | Ongoing | |
Library Building | San Narciso Builders Corporation | 14,519,355.43 | CTU Barili | 11/22/2018 8/18/2019 | GAA=15M | Ongoing | |
3-Storey Engineering Building (Phase 2) | JARC Construction and Marine Services Corporation | 9,665,000.00 | CTU Tuburan | 6/21/2018 2/15/2019 | GAA=10M | 1/15/2019 | Completed |
Teacher Education Building | NXBuild Construction | 9,669,699.91 | CTU Moalboal | 8/3/2018 3/30/2019 | GAA=10M | Ongoing | |
2-Storey Hospitality Management (HM) Building | BT Construction and General Services | 14,664,703.99 | CTU Daanbantayan | 11/30/2018 8/26/2019 | GAA=10M & STF=5M | Ongoing | |
2-Storey Extension Marine Engineering Building | CELJEM Construction and Development Corporation | 9,649,978.00 | CTU Carmen | 7/19/2018 3/15/2019 | GAA=10M | Ongoing | |
Veterinary Science Building | Gram Construction and Supply | 9,649,821.93 | CTU Barili | 5/19/2018 1/13/2019 | GAA=10M | 2/15/2019 | Completed |
Agriculture Building | DSJP Construction | 9,670,000.24 | CTU Argao | 5/10/2018 1/4/2019 | GAA=10M | 2/15/2019 | Completed |
Gymnasium | San Narciso Builders Corporation | 8,951,329.48 | CTU Danao | 7/2/2018 2/26/2019 | GAA=4.093M & STF=4.907M | Ongoing | |
2-Storey, 4-Classroom Building | JARC Construction and Marine Services Corporation | 9,635,000.00 | CTU Tabuelan | 4/25/2018 12/20/2018 | GAA=10M | 10/23/2018 | Completed |
2-Storey, 4-Classroom Building | CELJEM Construction and Development Corporation | 9,689,488.00 | CTU Bantayan | 6/14/2018 2/8/2019 | GAA=10M | 2/8/2019 | Completed |
Design & Build of the 9-Storey Administration Building | DUROS Development Corporation | 249,947,409.00 | CTU Main | 11/8/2018 6/29/2020 | STF=250M | Ongoing | |
2019 | |||||||
Research & Academic Building (Multi-Purpose Building & Perimeter Fence (Phase 2) | LCRB = 48,479,000.00 | CTUMain | GAA=50M | ||||
Administration Building with Library (Phase 2) | LCRB = 51,899,985.00 | CTU Danao | GAA=20M & STF=32M | ||||
Rehabilitation of Gymnasium | CTU Main | GAA=25M | |||||
3-Storey Administration & Education Building | CTU Dumanjug | STF=28M |